We’re scoping a mixed-use project by the Red Line where the transit agency’s easement review runs 10–12 weeks, while our land-use approval window is 8, and I’m trying to sequence milestones without slipping the construction start. Has anyone successfully front-loaded utility coordination or tightened P6 logic to bridge that gap and still hold the public hearing date?